
Welcome to the SD-6 High Priority Area (HPA) Page
(Everything on this page will apply only to the SD-6 HPA, and will be updated regularly. Please be patient as all the individual enhanced management pages are new and are subject to update at any time.)
Where is the SD-6 HPA?
It is the far Eastern HPA on the following map. The specific
sections included
are listed below the map.

Townships and Sections included in the SD-6 HPA shown on the above
map are:
TWP 7S-28W: Sections 19-21 and 28-33
TWP 7S-29W: Sections 4-9 and 16-36
TWP 7S-30W: Sections 19-36
TWP 8S-29W: Sections 1-18
TWP 8S-30W: Sections 1-18
TWP 8S-31W: Sections 22-27 and 34-36
Documents, Notices and other Important
Materials to the SD-6 Enhanced Management Process - in Chronological
Order:
1) HPA SD-6 Initial Introduction
and Hydrographs - November 10, 2008
2) LEMA Bill (SB 310)
- April 12, 2012 becomes law
3)
SD-6 Enhanced Management Proposal - Submitted July 16, 2012
4)
DWR Approval Notice - August 3, 2012
5)
Initial Public Hearing Notice - September 13, 2012 hearing
6)
GMD4 Oral Testimony at Initial Public Hearing
7)
Independent Hearing Officer's Report to Chief Engineer - October
4, 2012
8)
Second Public Hearing Notice - November 28, 2012 hearing
9) DWR Hearing Officer Instructions for November 28, 2012 hearing - Hearing Order 1
10) Initial LEMA Order of Decision - Signed December 31, 2012.
11) Final LEMA Order of Designation - Signed April 17, 2013.
SD-6 LEMA Special Newsletters:
Vol. 1, No. 1 - April 17, 2013>
DWR Webpage on SD-6 LEMA - All the official state information on
the LEMA. (Much of the same information is included on both
websites)
The Task 4 Process in SD-6:
Meeting Notes - Initial
Meeting (November 10, 2008)
Meeting Notes - Meeting 2
(February 4, 2009
Meeting Notes - Meeting 3 (June 17,
2009)
Meeting Notes - Meeting 4
(January 25, 2010)
Meeting Notes - Meeting 5
(February 17, 2010)
Meeting Notes - Meeting 6
(June 23, 2010)
Meeting Notes - Meeting
7 (December 16, 2010 - Joint DWR, GMD, SD-6 Mtg)
Meeting Notes - Meeting
8 (January 5, 2011 - Subcommittee work session)
Meeting Notes - Meeting
9 (January 11, 2011 - Subcommittee work session)
Meeting Notes - Meeting
10 (January 19, 2011 - Recommendations Adopted)
Meeting Notes - Meeting
11 (May 25, 2011)
Meeting Notes - Meeting
12 (March 28, 2012)
Meeting Notes -
Meeting 13 (May 9, 2012 - Final Mtg)
Narrative Chronological Summary from January, 2011:
January 19, 2011: Stakeholders approved a
Working Draft of their SD-6 HPA Recommendations and asked that
they be presented to the GMD 4 board. Moreover, that this draft be
the subject of the planned GMD 4 hearing scheduled for March 3,
2011.
March 3, 2011: The GMD 4 board conducted a public hearing on
the working draft which produced comments from five individuals that
were taken under consideration.
April 7, 2011: GMD 4 board adopts Stakeholder working draft and
begins incorporating the recommendations into the Northwest Kansas
Groundwater Management District Revised Management Program.
May 25, 2011: Stakeholder meeting following the public hearing
in which the stakeholders asked the GMD 4 board to NOT adopt the
proposal based on the stakeholder's request, and that new
legislative authority be sought to implement a locally developed
proposal such as theirs.
June 1, 2011: GMD 4 board honored the stakeholders' request
and declined to adopt the SD-6 enhanced management proposal. Staff
was directed to begin working on new Legislative authority for
implementing enhanced management areas as requested by the SD-6
stakeholders.
July 21, 2011: GMD 4 requests that the Governor's newly formed
Ogallala Aquifer Advisory Committee (OAAC) consider support for the
developing new enhanced management area legislation.
August 9, 2011: OAAC agrees to consider the new legislative
authority and discusses it in their initial meeting. GMD 4 manager
Wayne Bossert presented the concept of a special, local IGUCA to the
committee. Following the presentation, questions and more
discussion, the committee unanimously adopted the concept as
presented. This new effort was purposely segregated from the IGUCA
process, and hence was provided a new name - Local Enhanced
Management Area (LEMA).
Fall, 2011: GMD 4 staff begin working on a new Revised
Management Program - incorporating the concepts into the existing
Enhanced Management section.
January 19, 2012: The GMD 4 LEMA bill (co-drafted by GMD 4 and
DWR with technical help from the Revisor of Statutes, and with
multiple review and comment opportunities by the other 4 GMD's,
Kansas Farm Bureau, Kansas Livestock Association and Kansas Feed and
Grain Association) was introduced as SB 310 by Senator Ralph
Ostmeyer, Chairman of the Senate Natural Resources Committee.
April 5, 2012: The GMD 4 board approves the Revised Management
Program and submits it to the chief engineer.
April 12, 2012: Governor Signs new LEMA Bill (SB 310 - see
documents above) providing locals new authority to implement local
enhanced management plans.
May 9, 2012: Final working draft of the
SD-6 HPA enhanced management proposal is provided to the GMD 4
board.
May 16, 2012: Chief engineer reviews and approves the GMD
Revised Management Program.
July 12, 2012: GMD 4 board conducts required public hearing
RE: Revised Management Program for all GMD 4 members. The board also
approves the Revised Management Progam and sets it's effective date
as July 13, 2012.
July 16, 2012: GMD 4 board submits final SD-6 Enhanced
Management Proposal (see documents above) to chief engineer after
making 4 amendments to the draft provided on May 9, 2012. This
version includes the board amendments (unfortunately the embedded
spreadsheets did not remain clickable during the pdf conversion
process).
August 3, 2012: Chief engineer determines that the SD-6 LEMA
proposal meets the five statutory requirements and initiates the
LEMA process. He also schedules the initial public hearing for
September 13, 2012, in Hoxie, KS.
September 13, 2012: Chief engineer conducts the initial public
hearing through an independent hearing officer. GMD 4 staff and six
others testify.
September 26, 2012: GMD receives the remainder of the
testimony submitted to the initial public hearing process - 4
additional statements.
October 4, 2012: Independent Hearing Officer Constance Owen
issues her initial public hearing order - finding in the affirmative
on all three statements of fact. This order recommends to the Kansas
State Engineer that the SD-6 LEMA process continue.
October 10, 2012: Kansas chief engineer David Barfield accepts
initial hearing report and schedules second LEMA public hearing for
November 28, 10:30 AM in Hoxie, KS at the Sheridan County
Courthouse.
November 28, 2012: Kansas chief engineer David Barfield conducts the second required LEMA public hearing in Hoxie, KS at the Sheridan County
Courthouse. Following presentation of all testimony, the hearing record is left open through December 4, 2012 for any additional written
comments.
December 31, 2012: Kansas chief engineer David Barfield issued the initial SD-6 LEMA Order of Decision. This order establishes that: the LEMA period
is January 1, 2013 through December 31, 2017; individual allocations have been established for irrigation, stockwatering and recreational water rights therein
- based upon the local LEMA proposal; and several other details. The individual allocations and remaining specifics of the process will be provided to all water right owners
in the coming weeks.
January 22, 2013: The GMD 4 Board of Directors sends out individual notices that an Advisory Committee will be appointed in March
per the proposal, and invites all interested persons to consider serving.
March 7, 2013: Gmd4 board appoints the SD-6 LEMA Advisory Committee. Members are: Sharon Munk - representing non-irrigation; Gary Moss,
Brett Oelke, Grant Gaede, Dennis Rogers, Roch Meier and Stu Beckman - representing irrigation; Mitchell Baalman - representing GMD 4; and
Scott Ross - representing DWR.
March 28, 2013: The advisory committee meets for the first time to organize and discuss alternative meter methods that can be pre-approved for use.
Gary Moss is selected as Chairman and five alternative metering methods are suggested for DWR adoption. In short, these
were: 1) Periodic meter readings and recordation; 2) Power Company records that can express operational hours; 3) Temperature sensors that can log when the
well is in operation; 4) Ag-Sense or similar Ag data service; and 5) a sturdy engine hour meter - remotely mounted.
April 17, 2013: Gmd4 sends out the first edition of the new SD-6 LEMA Ledger - a newsletter just for the stakeholders of SD-6. Four
issues are covered: 1) Alternative meter procedures (noting only three of the recommended five methods were adopted by DWR); 2) RMA limited irrigation
program information; 3) Governor Brownback's Ag efficiency task force and their demonstration approach; and 4) the Multi-Year Flexibility Account
(MYFA) option for all water rights.
April 17, 2013: Kansas Chief Engineer David Barfield signed the Order of Designation. This final order stipulates that GMD 4 is to send out
individual letters to all water right owners in the LEMA within 30 days. These letters will have each water right's 5-year allocation, will describe how each water
right will be affected by the order during the designated LEMA period, and other relevant information. Each water right is to receive a letter. the The full order
is to be posted on the DWR and GMD 4 websites with hard copies provided to the Register of Deeds in both Sheridan and Thomas Counties and
to the DWR Field Office in Stockton and GMD 4. When requested, DWR and/or GMD 4 are to mail a full copy of the order to any interested person who is affected.